Projects
Projects / /

New 138kV 25kV Substation



Owner: Brazos Electric Power Coop
Project Cost: $1,875,000
Start: April 2014
End: September 2014


General Scope of Project: 
This project consisted of constructing a new 138/25kV Substation. The scope of work included Site Preparation, Landscaping and Irrigation, Detention Pond, 112,000 sqft of Buffalo Grass Sod Treatment, Decorative Concrete Fence and Wrought Iron Gates, Installation of Foundations, Structural Steel, Bus Work, HV Electrical Equipment, Grounding, Conduit System, Control House & Relay Panels, and Control and Power Cables.

Summary of Services Rendered: 
Ernest P. Breaux Electrical was responsible for all procurement (of materials not furnished by the owner) and construction of the complete substation.



 