Natchitoches 69kV Transmission Line – Natchitoches, Louisiana

Owner: Cleco
Project Cost: $2,200,000
Start: November 2011
End: August 2011

General Scope of Project:

This project involved the Construction, Engineering and Procurement assistance of a new 7 mile 69kV transmission line on concrete and steel poles including one major river crossing from CLECO’s Clarence Substation to the City of Natchitoches. The river crossing consisted of (2) 200’ "H” type steel towers with 6’x40’steel cased concrete foundations. Stringing the conductor across the river at a span of 3,300’ was accomplished with helicopter services.

Summary of Services Rendered:

Ernest P. Breaux provided ROW Clearing & Restoration, Survey & Staking, Foundation Installation, Structure Erection & Framing, Conductor Stringing & Clipping, and OPGW Installation for this project.


 


 