NEW 161 KV TO 12.47 KV SUBSTATION

Owner: Southwest Tennessee Electric Membership Cooperative
Location: Burlison, Tennessee
Project Cost: $1,500,000
Start: September 2011
End: June 2012

General Scope of Project: This project involved elevating an existing 138/25 kV substation. The scope of work included construction of new foundations and structural steel required to elevate an existing station due to flooding after hurricane Katrina and Rita. Ernest P. Breaux Electrical was responsible for all procurement (of materials not furnished by the owner) and construction of the complete substation.


 


 